Location: Bowmanville, Municipality of Clarington, ON
Summary
The Darlington project is for the site preparation, construction, operation, decommissioning and abandonment of up to four new nuclear reactors at the existing Darlington Site to generate approximately 4,800 megawatts of electricity to the Ontario grid.
Licensing Progress Details (Timelines are best estimates and are subject to change)
Environmental Assessment and Site Preparation |
||||
Project Milestone |
Responsibility |
Date |
Comment |
|
CNSC and other Federal Authorities |
Applicant |
|||
Ontario Power Generation applies for a Licence to Prepare Site (PDF) |
|
September |
|
|
Notice of Environmental Assessment (EA) posted Read Project Description (PDF) - in English only |
|
May |
Additional information was required to complete the Project Description. This was completed in 2007 and allowed the Environmental Assessment to start. |
|
Federal Minister of Environment refers EA to a Joint Review Panel (JRP) |
|
March |
|
|
Draft Environmental Impact Statement (EIS) Guidelines and JRP Agreement published for comments |
|
September |
|
|
Comment period on draft Environmental Impact Statement Guidelines and JRP Agreement Read Comments |
|
September |
Opportunity for the public, Aboriginal groups and other stakeholders to review and provide comments. |
|
|
March 2009 |
Finalized by the federal Minister of the Environment, in consultation with the President of CNSC, based on comments received. |
||
| Major Projects Management Office (MPMO) Project Agreement signed(source: MPMO) |
|
May |
An MPMO Project Agreement (source: CEAA) is an agreement between federal Deputy Ministers that outlines the process by which federal departments or agencies will carry out their particular roles or responsibilities during the federal regulatory review of a proposed major resource project. The agreement includes a timeline and schedule for the completion of the regulatory review with regular milestones to allow tracking of progress. |
|
Ontario Power Generation submits the EIS with documentation |
|
September |
|
|
|
October 2009 |
Appointed by the Minister of the Environment and the Governor in Council in consultation with the President of CNSC.
|
||
Notice of EIS review period (Source: CEAA) |
|
November |
JRP announces the start of the EIS review period with instructions to provide comments. |
|
Public Comment Period Review of EIS, including public review Read comments (source: CEAA) |
Led by JRP |
November 2009 to May 2010 * The end date for the comment period will be revised and extended as a result of the request by the JRP for additional information from OPG. Consult information below for more information. Other project milestones would be modified accordingly. |
Six-month comment period** led by JRP, including conformity and technical review of the EIS and complete application for Licence to Prepare Site. Review opportunity for the JRP, public, Aboriginal groups and other stakeholder for comments. **Six-month comment period excludes time used by applicant to respond to JRP requests. The comment period is extended when there is a request for information by the JRP. The comment period’s end date will be determined according to the amount of time the applicant requires to respond to the JRP’s request. |
|
Public notice of technical information session held on December 15, 2009 in Ottawa (source: CEAA Web site) Consult presentations and transcripts (source: CEAA Web site) |
|
December 2009 | JRP invited the public to attend a technical information about nuclear power plant designs based on three reactor technologies | |
Information Request 1 JRP requests from Ontario Power Generation additional information regarding their EIS and complete application (source: CEAA) JRP letter of request for additional information (source: CEAA) |
|
February 2010 | JRP sends a letter to Ontario Power Generation requesting for additional information concerning the EIS and complete application for a Licence to Prepare a Site, submitted by Ontatio Power Generation in September 2009 (source: Ontario Power Generation). The request is as a result of the JRP and the public’s review of the documents. | |
| Ontario Power Generation responds in February and in March to the JRP Information Request 1 of February 2010 – in English only. (PDF) (Source: CEAA) |
|
February and March 2010 | Ontario Power Generation responds to JRP’s Information Request 1, concerning the EIS and application for a Licence to Prepare Site submitted by Ontario Power Generation (Source OPG) | |
Notice of Public Hearings posted |
To be determined by JRP |
|
Pending |
|
JRP holds Public Hearings |
Expected from JRP |
September to October 2010 |
To hear views about the EIS and the application for a Licence to Prepare Site from the public, Aboriginal groups, Ontario Power Generation and other stakeholders. |
|
JRP submits Report to Federal Government |
Expected from JRP |
December |
The Report is published and the presented by the Minister of the Environment to the Governor in Council. |
|
Federal Government’s Response to Report |
Expected from the Governor in Council |
February 2011 |
The Governor in Council responds whether the project may proceed or not. |
|
JRP issues Licence to Prepare Site |
Expected from JRP |
April |
If the Governor in Council’s response is that the project may proceed, the JRP could issue Licence to Prepare Site. |
|
Construction |
||||
Project Milestone |
Responsibility |
Date |
Comment |
|
CNSC and other Federal Authorities |
Applicant |
|||
Ontario Power Generation applies for Licence to Construct |
Expected from OPG |
3rd - 4th quarter 2011 (to be determined) |
|
|
CNSC hold Public Hearings |
Expected from CNSC |
2014 | CNSC holds hearings on the Ontario Power Generation application for a Licence to Construct and decides on the application. |
|
Operation |
||||
Project Milestone |
Responsibility |
Date |
Comment |
|
CNSC and other Federal Authorities |
Applicant |
|||
Ontario Power Generation applies for Licence to Operate |
|
Expected from OPG |
2016 |
|
CNSC holds Public Hearings |
Expected from CNSC |
|
2018 |
CNSC holds Public Hearings on the Ontario Power Generation application for a Licence to Operate and decides on the application. |
Decommissioning |
||||
Project Milestone |
Responsibility |
Date |
Comment |
|
CNSC and other Federal Authorities |
Applicant |
|||
Ontario Power Generation applies for a Licence to Decommission |
|
Expected from OPG |
2076 |
|
CNSC holds Public Hearings |
Expected from CNSC |
|
2078 |
CNSC holds Public Hearings on the Ontario Power Generation application for a Licence to Decommission and decides on the application. |
Abandonment |
||||
Project Milestone |
Responsibility |
Date |
Comment |
|
CNSC and other Federal Authorities |
Applicant |
|||
Ontario Power Generation applies for Licence to Abandon |
|
Expected from OPG |
2088 |
|
CNSC holds Public Hearings |
Expected from CNSC |
|
2090 |
CNSC holds Public Hearings on the Ontario Power Generation application for a Licence to Abandon and decides on the application. |