DCSIMG
Canadian Nuclear Safety Commission
Symbol of the Government of Canada

Canadian Nuclear Safety Commission

Protocol for National Research Universal Licensing Activities

January 2010, Revision 1

  • Atomic Energy of Canada Limited (AECL) and the Canadian Nuclear Safety Commission (CNSC) have signed a protocol for National Research Universal (NRU) licensing activities.
  • The protocol establishes a framework to prepare the necessary information for the CNSC to assess the continued operation of the NRU reactor beyond the current licence period. The NRU licence expires October 31, 2011.
  • Licensing activities for NRU will take place within the wider context of the licence renewal for Chalk River Laboratories, taking into account the Directive to CNSC, issued by the Governor in Council. The CNSC will take into account the health of Canadians who, for medical purposes, depend on nuclear substances produced by NRU as an input for evaluating various licensing options, while protecting the health, safety and security of Canadians and the environment.
  • Revision 1 of the protocol signed in January 2010 replaces the original version of the protocol signed in July 2008.


Table of Contents

Summary of Changes

Extent of the Protocol

1. Objective
2. Introduction
3. Approach to Licensing
4. Schedule
5. Roles and Responsibilities

5.1 CNSC Governance Structure
5.2 AECL Governance Structure

6. Organization Representatives
7. Statement of Work

7.1 NRU Relicensing technical scope
7.2 Activities and Deliverables
7.2.1 Document Deliverables
7.2.2 Other deliverables
7.2.2.1 Common Deliverables
7.2.2.2 AECL Additional Deliverables
7.2.2.3 CNSC Additional Deliverables
7.3 Conflict Resolution Process

8. Future Revisions of the Protocol
9. Extended Outage Impact on the NRU ISR
10. References
11. Glossary of Terms


Summary of Changes

Section

Change

 

Title “Extent of the Protocol” added and the purpose of revision defined

5.2

AECL Governance Structure revised by AECL

6.0

AECL Organization Representatives revised by AECL

7.1

NRU Relicensing Technical Scope updated and modified to show completions

Periodic press releases not included in the scope for Phase I to III

7.2.1

Document Deliverables Table updated and the status of deliverables shown

7.2.2.1

Working Level Meetings” updated to indicate changes by both Organizations

“Quarterly Reports” revised to indicate the role of each organization

7.2.2.2

AECL’s responses to actions from meetings between AECL and CNSC and submission of supporting documents modified to include AECL’s acceptance and agreement

7.2.2.3

CNSC Additional Deliverables on EA updated

9.0

A section titled “Extended Outage Impact on the NRU ISR” added

10.0

References updated

11.0

Glossary updated

Top

Extent of the Protocol

This protocol is essentially administrative in nature. Nothing in this protocol or any statement in this protocol is to be construed or interpreted as affecting the jurisdiction and discretion of the Commission in any assessment of any application for licensing purposes under the Nuclear Safety and Control Act (NSCA). It is not intended to constitute a deviation or inference to a proposed amendment to the current licence for the National Research Universal (NRU).

This revision reflects that developments in NRU ISR management and process that have occurred since the initiation of the original protocol [1]. The impact of the extended outage to repair the NRU vessel leak is addressed in this revision of the protocol.

Top

1.     Objective

The objective of this protocol is to provide a framework within which AECL and CNSC staff will work to prepare the necessary information for the Commission to assess the continued operation of the NRU reactor beyond the current licence period. NRU is operated under the Nuclear Research and Test Establishment Operating Licence for Chalk River Laboratories[2]that expires October 31, 2011. Licensing activities for NRU will take place within the wider context of licence renewal for Chalk River Laboratories, taking into account the health directive for the disruption of isotope production as an input for evaluating various options without compromising safety.

Top

2.     Introduction

The legal framework for licence renewal is derived from the Nuclear Safety and Control Act (NSCA) [3] and supporting Regulations.

Following the Directive [4] from the Governor in Council, in considering all the risk to Canadians, the AECL and CNSC staff are coordinating their effort for the licensing of the NRU, to meet the mandates and accountability responsibilities of both organizations.

In engaging in this coordinated effort and working responsibly in the public interest, the CNSC maintains its independence as the Canadian Nuclear regulator and AECL continues to be solely responsible for the safe operation of the NRU reactor.

It is understood that:

  • safety will not be compromised in making licensing recommendations to the Commission;
  • the licensing activities will be conducted on a best effort basis to minimize, to the extent possible, disruption of the production of medical isotopes; and
  • the objective is to produce a comprehensive body of information and recommendations to allow the Commission to render its decision regarding the application for a licence renewal.

This protocol sets out the framework within which both organizations will work and establishes a high level estimate of the timeline.

Top

3.     Approach to Licensing

To fully address the responsibilities for safety and accountability, and to serve the Canadian public, both the Canadian Nuclear Safety Commission and Atomic Energy of Canada Limited recognize the importance of a well-planned and coordinated working arrangement.

Both organizations recognize the complexity of the matter and agree to implement an Integrated Safety Review (ISR) of the facility. The ISR process for NRU will be fully defined at an early stage of the work process. It will rely on the guidance set out in the IAEA Safety Guide: Periodic Safety Review of Nuclear Power Plants [5], and the CNSC Regulatory Document: Life Extension of Nuclear Power Plants [6], recognizing that NRU is a research facility approaching licence renewal not a power plant undergoing life extension.

Top

4.     Schedule

The schedule set out in the statement of work in this protocol is intended to align with the timeline for the site licence renewal in 2011 and the lead time notices required in the Canadian Nuclear Safety Commission Rules of Procedure.

It is recognized that the schedule includes a large amount of work and there may be execution risks that could cause delays. To preserve the completion of the objectives, the delay risks will be dealt with in a timely manner through adjustments of resources or the time line of this protocol. These adjustments will be made through the protocol revision process outlined below.

Top

5.     Roles and Responsibilities

5.1     CNSC Governance Structure

The CNSC has created the NRU Licensing Extension Steering Committee (NRULESC) to provide strategic level direction and senior management oversight and support to the programs associated with the NRU licensing extension beyond 2011.

The NRULESC is chaired by the Executive VP, Regulatory Operations Branch (ROB) and formed by all relevant executive directorates, including:

  • Vice-President of the Technical Support Branch;
  • Vice-President of the Regulatory Affairs Branch;
  • Director General of the Directorate of Nuclear Cycle and Facilities Regulations;
  • Director General of the Directorate of Assessment and Analysis;
  • Director General of the Directorate of Environmental and Radiation Protection and Assessment;
  • Director of Chalk River Laboratories Compliance and Licensing Division;
  • Director of Reactor Thermalhydraulic Division;
  • Project Manager (Secretary)

The objectives of the Steering Committee are to enable CNSC staff to fulfill its mandate of providing recommendations to the Commission regarding the re-licensing of the NRU in 2011. Its enabling function is fulfilled by ensuring that the NRU licensing activity:

  • receives appropriate priority;
  • is adequately resourced;
  • progresses;
  • is conducted in accordance with project management practices;
  • contains appropriate review plans;
  • is consistent in its application and requirements; and
  • follows agreed process and technical direction.

The NRULESC is directly accountable to the CNSC President through the EVP ROB.

Top

5.2     AECL Governance Structure

AECL has established a Site Senior Management Review Team (SSMRT) to review and approve the recommendations from the NRU ISR. This team is led by the Senior Vice-President CRL and Chief Nuclear Officer, and includes representation from CRL Operations and Regulatory Affairs, as follows:

  • Vice President and General Manager Operations
  • General Manager, Programs and Nuclear Oversight, and Chief Regulatory Officer
  • General Manager, Engineering and Projects, Chief Nuclear Engineer
  • Director, NRU Operations and Facility Authority
  • General Manager, Isotope Supply Reliability Program
  • Chairman of the Safety Review Committee (as an observer)
  • NRU ISR Safety and Licensing Manager (Secretary)

Top

6.     Organization Representatives

The organization representatives for these activities (ORs) are responsible for all matters concerning the work under this Protocol and bring the matter to their respective governance bodies, should problems arise during the work that may affect the schedule or the scope of the work.

For the purposes of this Protocol, CNSC staff shall be represented by:

  1. The Director, CRLCL Division, DNCFR (position currently held by M. Santini), for matters related to governance
    Telephone Number: 613-943-2923
    Mobile Telephone: 613-222-2064
    Fax Number: 613-995-5086
    e-mail: Miguel.Santini [at] cnsc-ccsn [dot] gc [dot] ca

  2. The NRU LE-Project Manager (position currently held by B. Pearson) for matters related to implementation
    Telephone Number: 613-996-9056
    Mobile Telephone: 613-282-7577
    Fax Number: 613-995-5086
    e-mail: Bruce.Pearson [at] cnsc-ccsn [dot] gc [dot] ca

For the purposes of this Protocol, AECL shall be represented by:

  1. The Manager, Operations Safety and Licensing (position currently held by D. Garrick) for matters related to governance
    Telephone Number: 613-584-8811 ext.43683
    Mobile Telephone: 613-633-0225
    e-mail: dgarrick [at] aecl [dot] ca

  2. The NRU ISR Safety and Licensing Manager (position currently held by J. Frits) for matters related to implementation
    Telephone Number: 613-584-8811 ext.43102
    Mobile Telephone: 613-639-1917
    e-mail: fritsjl [at] aecl [dot] ca

Either Party hereto may, by written notice, change any of its appointees mentioned above.

Top

7.     Statement of Work

This set of high level tasks/milestones are derived from the ISR process documented in RD-360. It is recognized that work performed in support of relicensing in 2005 and 2006 provides a basis for a comprehensive ISR. The work described in this protocol builds on that basis.

This protocol defines the high-level structure of the ISR process that will be followed. An early activity will be to gather the necessary information to form a complete Level I plan, with milestones and deliverables.

Top

7.1     NRU Relicensing technical scope

The technical scope of the work includes the production, review of documentation generated in the Integrated Safety Review of the NRU Reactor for the licence renewal in 2011, presentation of recommendations to the Commission in relation of the licence renewal, and related design upgrades of the NRU reactor as determined by the Commission in the operating licence.

This scope is divided in four phases.

Phase I

Definition and development of a specific ISR approach for NRU

Assessment of Status Quo– Complete

Level I project Plans– Complete

ISR scope and basis – Complete

Phase II

Integrated Safety Review execution

Level II Project Plan – Complete

Presentation to the Commission at mid-Term (CMDs) –Complete

Safety factors reports (production and assessment)

EA Screening Report Decision

Global Assessment Report production and CNSC assessment; and IIP production and CNSC assessment and acceptance

Phase III

Licence renewal

Production and submission of CMDs to the Commission for Licensing decision

Presentations to the Commission

Phase IV

Improvement Implementation Program start

Scope to be determined

The time periods for each phase are shown in Section 7.2

The scope for Phase I to III include:

  1. Development and review of documents described in Section 7.2, that will be updated as necessary and agreed in writing by both parties, and such other documents that may be necessary to support the topical reviews.
  2. Discussion of any issues arising from the work performed under this protocol that could be considered as a potential barrier to future operation of NRU. Set-up and implement a conflict resolution mechanism on the technical issues described in Section 7.3.
  3. Quarterly reporting, in format agreed by the parties, of technical and schedule progress and percentage of work completed.
  4. Periodic reporting to Government on progress.
  5. AECL request of licence renewal of the reactor and establishment of the expected life of the reactor.
  6. CNSC staff issuance of a recommendation to the Commission with respect to licence renewal beyond 2011.

Scope and timetable for Phase IV is to be determined during the execution of the previous phases.

Top

7.2     Activities and Deliverables

The deliverables in the following sections are divided in:

  • Documents
  • Other Deliverables
  • Common Deliverables
  • Meetings
  • Quarterly Reports
  • AECL Additional Deliverables
  • CNSC Additional Deliverables

Top

7.2.1     Document Deliverables

Document Deliverables

Target Dates

Status and Actioned Organization(s)

Phase I

Comprehensive list of issues produced for NRU, from ImpActs, fire hazard assessment, previous safety assessments, audits, licensing correspondence etc.

August 2008

Complete
AECL

Risk prioritization of outstanding issues in the current Licensing Strategy document [7]

August 2008

Complete

CNSC / AECL

Discussions and agreement on the scope of key issues including:

- Tritium issues in coolant and bays
- Waste management strategy

October 2008

Complete

CNSC / AECL

Discussions on whether EA is required and if so its scope

October 2008

Complete

CNSC / AECL

Complete Level I project plan

November 2008

Complete

AECL

Complete Level I review plan

November 2008

Complete

CNSC staff

Discussions and agreement on ISR scope and project plan

December 2008

Complete

CNSC / AECL
     

Phase II

ISR Basis

March 2009

Complete

AECL

EA determination for the cumulative effects from the proposed extended long-term operation

March 2009

Complete

CNSC staff

Acceptance of ISR Basis Document[8]

April 2009

Complete

CNSC staff

Complete Level II coordinated project plans

May 2009

Complete

CNSC / AECL

EA Guidelines for relicensing to the Commission [9] and[10]

June 2009

Complete

CNSC staff

ISR presentation (mid-term report for CRL site licence) to the Commission for information

2009

Complete

CNSC / AECL
Delivery of first set of Safety Factor Reports (8-17) January 31, 2010 AECL

Environmental statement report

January 2010

AECL

Delivery of second set of Safety Factor Reports (1-7)

March 31, 2010

AECL

EA Screening Report

July 2010

CNSC staff

Complete CNSC Staff assessment of Safety Factors Report

October 31, 2010

CNSC staff

CNSC decision on EA approval

November 2010

CNSC Commission

Global Assessment Report and IIP Submission

January 31, 2011

AECL

Global Assessment Report assessment and IIP assessment and acceptance

April 2011

CNSC staff

     

Phase III

CMDs for Hearing Day One

April 2011

All

Licence renewal Day One

June 2011

All

CMDs for Hearing Day Two

July 2011

All

Licence renewal Day Two

September 2011

All

CNSC licensing decision

October 2011

CNSC Commission

     

Phase IV

If NRU operation continues under a renewed licence

IIP starts as per ISR – Detailed Project Plan to be developed

Top

7.2.2 Other deliverables

7.2.2.1 Common Deliverables

Meetings

Working Level Meetings

Monthly AECL / CNSC review meetings will be held to review progress on the work and highlight any potential major issues or disputes. Attendance at these review meetings will be, two or more of,

  • Director CRLCLD (CNSC)
  • Project Manager CRLCLD (CNSC)
  • Backup Project Manager CRLCLD (CNSC)

two or more of,

  • Manager, Operations Safety and Licensing (AECL)
  • NRU ISR Safety and Licensing Manager (AECL)
  • Director, ISRP Safety and Licensing (AECL)
  • Manager, ISRP Safety Assessment (AECL)

Technical Meetings

Meetings between technical experts at the CNSC and AECL will be arranged as the need arises. The organization representatives, or their designates, will participate in technical meetings to provide continuity across licensing activities.

Executive Meetings

To be arranged quarterly or more frequently to follow up progress and/or deal with the conflict resolution process. Minimum attendance at these Executive meetings will be the Executive VP ROB from CNSC; and SVP CNO from AECL.

Quarterly Reports

Quarterly reports to the respective Governance (Sections 5.1 and 5.2) and Presidents are to be prepared by one organization and reviewed by the other with roles alternating for each submission.

Other Updates

Coordinated periodic updates to Government on progress will be prepared and presented by AECL. AECL and CNSC staff will review and contribute to third party updates. 

Top

7.2.2.2     AECL Additional Deliverables

In addition to the deliverables described in previous sections, AECL will deliver:

  • EA impact statements;
  • CMDs as required; and
  • For Phases I to III, AECL will provide responses to actions from meetings between AECL and CNSC representatives pursuant this Protocol and submit any supporting documents that may be required to address issues identified.

Top

7.2.2.3     CNSC Additional Deliverables

In addition to the deliverables described in previous sections, CNSC will deliver:

  • EA screening report for re-licensing;
  • CMDs as required;
  • Letters on submissions indicating the general acceptability or otherwise of the submission or topics and identify any items for resolution; and
  • Any issues relating to NRU relicensing or licensability identified by CNSC in the course of the reviews will be resolved by a closure letter or documented path forward.

Top

7.3.     Conflict Resolution Process

CNSC staff and AECL staff have agreed to coordinate licensing work related to NRU operation beyond 2011 under the Nuclear Safety and Control Act. Disagreements may arise during the execution of the work. A review and dispute resolution mechanism will be used during the review to ensure fairness and assist timely completion.

Step 1: Identification of the Issue & Resolution at the staff level

  1. Monthly AECL/CNSC review meetings will be held to review progress and highlight any potential major issues or disputes.
  2. The framework for a decision on an issue will be the Government policies on regulatory effectiveness and the licensing requirements stated in, or referenced in, the ISR Basis Document, once this has been agreed to by both parties.
  3. It is the intention of both parties to resolve issues at this level.
  4. If an issue cannot be resolved at this level, it will be documented (typically, a brief factual summary of the issue and a paragraph representing the view of each organization) by the individuals in Paragraph 1 within two weeks of failure to resolve, and forwarded to the Senior Management Level (Step 2).

Step 2: Resolution at the Senior Management Level

  1. A Step 1 issue, once documented, will be provided to the Director General, Directorate of Nuclear Cycle and Facilities Regulations (CNSC), the Director General, Assessment and Analysis (CNSC), the General Manager Programs and Nuclear Oversight (AECL), and the Vice President and General Manager CRL Operations (AECL) for resolution. A meeting will be called, normally within 30 days, to resolve the issue, and the resolution documented.
  2. Issues that cannot be resolved at this level will be referred to the Executive Vice-President Level (Step 3) within two weeks, supported by the original or revised documentation from Step 1.

Step 3: Resolution at the Executive Level

A Step 2 issue, with documentation, will be sent to the Executive Vice President, Regulatory Operations Branch (CNSC) and the Senior Vice President and Chief Nuclear Officer (AECL) for resolution. A meeting will be called, normally within 30 days, to resolve the issue, and the resolution documented.

Top

8.     Future Revisions of the Protocol

Revisions of this protocol will be coordinated by the organization representatives and must be approved by the organizations’ governance structures and Presidents.

Revisions may include:

  1. Adjustments to the time table;
  2. Inclusion of temporary licence extension strategy; and
  3. Other revisions as required.

Top

9.     Extended Outage Impact on the NRU ISR

The extended outage associated with repair of the NRU vessel leak and NRU return to service has had an impact of the NRU ISR. As part of the Extended Activities Program (EAP) some refurbishment work is being performed on NRU that otherwise would not necessarily have been completed prior to finishing the NRU ISR. As a result, some of the recommendations that would have come from the Global Assessment will already have been addressed. 

Top

10.     References

[1] Protocol for National Research Universal Licensing Activities, July 15, 2008 [Return]

[2] Nuclear Research and Test Establishment Operating Licence, Chalk River Laboratories, NRTEOL-01.01/2011 [Return]

[3] Nuclear Safety and Control Act , 1997, c.9 N-28.3 [Return]

[4] Nuclear Safety and Control Act, Directive from Governor in Council to the Canadian Nuclear Safety Commission Regarding the Health of Canadians, SOR/2007-282[Return]

[5] IAEA Safety Guide, Periodic Review of Nuclear Power Plants, NS-G-2.10, 2003 [Return]

[6] Regulatory Document Life Extension of Nuclear Power Plants RD-360, February 2008 [Return]

[7] Licensing Strategy for AECL’s NRU Licensability Extension project, Lamarre to McGee, 2006 February 28 (referenced by Condition 19 in the CRL Licence). [Return]

[8] NRU Integrated Safety Review (ISR) Basis Document, April 28, 2009 [Return]

[9] Scoping Information Document - NRU Reactor Long-term Management Project AECL CRL, June 30, 2009 [Return]

[10] Record of Proceedings - Atomic Energy of Canada Limited - Proposed Environmental Assessment Scoping Information Document for the National Research Universal Reactor Long-Term Management Project at Chalk River Laboratories, July 16, 2009 [Return]

Top

11.     Glossary of Terms

AECL Atomic Energy Canada Limited
CMD Commission Member Document
CNSC Canadian Nuclear Safety Commission
CNO Chief Nuclear Officer (AECL)
CRL

Chalk River Laboratories

CRLCLD Chalk River Laboratories Compliance and Licensing Division (CNSC)
DNCFR Directorate of Nuclear Cycle and Facilities Regulation
EA Environmental Assessment
IIP Integrated Implementation Plan
ISR Integrated Safety Review
LE Licensing Extension
NRU National Research Universal reactor
NRULESC NRU Licensing Extension Steering Committee (CNSC)
OR Organization Representative (see Section 6)
PSR Periodic Safety Review
ROB Regulatory Operations Branch (CNSC)
SSMRT

Site Senior Management Review Team (AECL)

SVP Senior Vice-President

Top

H. MacDiarmid President and Chief Executive Officer ATOMIC ENERGY OF CANADA LIMITED Date: January 11/10 M. Binder President and Chief Executive Officer CANADIAN NUCLEAR SAFETY COMMISSION Date: January 07/10